\section{Progress}
|
||||||
|
We are nearing completion on the virtual machine upon which the debugger will
|
||||||
|
run. Moving forward, the front end team will polish the existing interface, and
|
||||||
|
expand it to control the debugger. The back end team will work on the core
|
||||||
|
functionality of the debugger and continue to fix bugs with the virtual machine.
|
||||||
|
This places us two weeks behind schedule over all, as we planned to have the
|
||||||
|
virtual machine finished by April 1\textsuperscript{st}.
|
||||||
|
|
||||||
|
\subsection*{Front End: Status}
|
||||||
|
The front end team is keeping pace with the back end team, but is still two
|
||||||
|
weeks behind schedule. We have a working interface where users can input,
|
||||||
|
compile, and run C0 programs, but there are no debugging features.
|
||||||
|
|
||||||
|
\subsection*{Front End: Projections}
|
||||||
|
We will modify our schedule to allow more time for the work on the debugger.
|
||||||
|
This time will come from a shortened user testing and revision period. That
|
||||||
|
said, because of our thorough work on the virtual machine, implementing the
|
||||||
|
debugger should progress more rapidly than originally planned. The modified
|
||||||
|
schedule is depicted in our updated Gannt chart (Figure \ref{gannt}).
|
||||||
|
|
||||||
|
\subsection*{Back End: Status}
|
||||||
|
The back end team is also two weeks behind schedule. The virtual machine, along
|
||||||
|
with most library functions needed to run programs, is complete and working
|
||||||
|
well. The team has started working on stepping through program execution, but
|
||||||
|
those features have not yet been incorporated with the rest of the application.
|
||||||
|
|
||||||
|
\subsection*{Back End: Projections}
|
||||||
|
In the coming time, the back end team will implement the remaining library
|
||||||
|
functions, then transition all of their efforts to the debugging features. Like
|
||||||
|
the front end team, this transition was originally scheduled for
|
||||||
|
April\textsuperscript{st}, but will now occur in the next week.
|
||||||
|
|
||||||
|
\includegraphics{gannt}
|
||||||
|
|
||||||
|
Our revised Gannt chart features two key changes. The back end and front end
|
||||||
|
sections were modified such that the transition of effort from the virtual
|
||||||
|
machine to the debugger aligns with where that actually happened. As a result,
|
||||||
|
the testing and revision section was push back. We are now aiming to start
|
||||||
|
testing and revision the week of April 20\textsuperscript{th}.
|
||||||
|
|
||||||
|
\subsection*{Quantification of Progress}
|
||||||
|
Currently, we have over 50 test files that we use to check for correctness of
|
||||||
|
our virtual machine. We currently pass 44 test cases, and are working to have
|
||||||
|
the rest functioning correctly soon. Once the debugger is more feature complete,
|
||||||
|
we will focus more on user feedback to assess progress.
|
||||||